PRESERVE INFRASTRUCTURE

Interstate

High Volume Non-Interstate

Low Volume  

Bridge Conditions

Performance Goal:

Maintain an acceptable ride quality (fair or better) on all Interstate and High Volume roadways. Maintain a bridge system rated in good condition and expand bridge management efforts by preparing a plan for every structure based on preservation, rehabilitation and replacement needs. 

Verified Mix Designs

Asphalt Mix Designs are checked for durability and consistency. 

GOAL: Verify 75% of Mix Designs within 6 days and 100% within 10 Days

Certifications

All Trans Techs are fully certified each year. Graph below shows how certifications were achieved. 

Trans Techs                         get things done!

2016 Construction Accomplishments:

Change Orders:

  • $3.44 Million
  • 1.96 change orders per project
  • Change Orders 3,3% of contract value
  • 39 projects with either negative or zero dollar change orders

Notable Projects:

  • I-15; Beaver Ridge Climbing Lanes
  • I-15; Pine Creek Climbing Lanes
  • Southern Parkway Segment 3B
  • SR-9; LaVerkin
  • I-70 Slab Repair
  • US-191; Blanding to devil's Canyon
  • SR-25; Fishlake Highway
  • I-70; Spotted Wolf Canyon
  • US-6; Summit to White River

2016 Maintenance Accomplishments: 

Special Projects 

30 betterments constructed by Region Four maintenance crews
  • Culvert Extensions
  • Cattle Guards
  • Drainage Work
  • Shouldering
  • Overlays
  • Scour projects
36 Contractual Betterments
  • Wildlife and Livestock Fencing
  • Brush and tree removal
  • Guardrail
  • Asphalt overlays
  • Flood Repair

49 projects under construction in calendar year 2016 ($110.8 Million Original Contract amount)

Project Closeout table